Environmental clearance under the EIA Notification 2006 is a mandatory pre-condition for scheduled projects. The quality of the EIA, the management of the public consultation and the terms of the clearance conditions shape the project’s entire operational life.
An environmental clearance under the EIA Notification 2006 is not a rubber-stamp approval. It is a regulatory determination that the project can proceed subject to conditions — conditions that are binding, monitorable and enforceable. The quality of the EIA report, the completeness of the baseline data, the adequacy of the public-consultation process and the terms of the clearance conditions all determine whether the project will face challenges before the NGT, conditions that are commercially unimplementable, or compliance failures that invite enforcement action.
AMLEGALS advises project proponents from the screening stage through appraisal and post-clearance compliance. The strategy is set before the first filing — the categorisation of the project, the scope of the EIA, the management of the public hearing and the negotiation of clearance conditions are all legal decisions that have commercial and operational consequences. A clearance obtained without strategic legal input is a clearance vulnerable to challenge and difficult to comply with.
Determining the category (A, B1 or B2) and the applicable clearance authority for the project.
Advising on Terms of Reference, coordinating with EIA consultants and ensuring the EIA report addresses all statutory and environmental requirements.
Managing the public hearing process, preparing proponent responses and ensuring procedural compliance.
Representing the proponent before the Expert Appraisal Committee or SEAC, responding to queries and securing the clearance with implementable conditions.
Monitoring and ensuring compliance with clearance conditions, half-yearly returns and environmental management plans.
Defending environmental clearances challenged before the National Green Tribunal, including interim and stay applications.
The Schedule to the EIA Notification 2006 lists the activities that require prior environmental clearance. These include mining, thermal power, river valley, ports, highways, industrial estates, petrochemicals, cement, building and construction above the prescribed thresholds, and expansion or modernisation of existing projects that increase capacity beyond stipulated limits. The 2020 draft amendments proposed changes to the thresholds and categorisation.
Category A projects are appraised at the Central level by the Expert Appraisal Committee of the MoEFCC. Category B projects are appraised by the State-level Expert Appraisal Committee and cleared by the State Environment Impact Assessment Authority (SEIAA). Category B is further divided into B1 (requiring full EIA including public consultation) and B2 (exempt from EIA).
Public consultation under the EIA Notification 2006 involves two components: a public hearing conducted at or near the project site, where affected persons can raise environmental concerns, and written responses from stakeholders. The public-hearing proceedings are recorded and must be placed before the Expert Appraisal Committee. The proponent must address each concern in the final EIA report.
Environmental clearances are typically granted for a specified period — the construction phase validity varies by project type (generally 7 to 10 years for construction, with operational validity linked to the project lifecycle). The clearance is subject to compliance with the conditions stipulated, and non-compliance can result in suspension, revocation or NGT proceedings.
Yes. An environmental clearance can be challenged before the National Green Tribunal under Section 16 of the NGT Act 2010 within 30 days of the grant (with a 60-day condonation). Challenges are typically grounded in procedural violations — deficient EIA, inadequate public consultation, non-application of mind by the EAC — or substantive violations such as clearance for a prohibited area or in excess of carrying capacity.